The steel skeleton of the 'Bird's Nest' to fall by no more 30cm

Update:2007-05-22 15:05:37

(BEIJING, Sept. 17) -- The month-long unloading process for the birds nest-shaped steel skeleton of the National Stadium for the Beijing Olympic Games welcome the ultimate moment on Sunday morning: 78 bracketing structures that support the weight of its steel skeleton will be gradually removed.

Therefore, parts of its steel skeleton will be lowered for less than 30cm, according to the experts.

The large steel skeleton of the project weighs 42,000 tons, with the roof and the hanging parts around it accounting for 11,200 tons. To bear such a heavy load, 78 supporting structures were temporarily installed and distributed in different points under stress, with 24 structures along the outer circle, 24 in the middle circle and 30 in the inner circle. What awaits the technicians and workers is to discharge all these supporting objects from a weight of 11,200 tons.

The unloading process of the supporting structure is divided into seven steps and each step is conducted in the order of outer circle, middle circle, inner circle, middle circle and inner circle. Therefore, 35 sub-steps are needed to complete the whole process.

According to the plan, the outer circle will vertically drop by 67-70mm, the middle by 161-178mm and the inner by 208-286mm.

主编: 唐岩 高级编辑: 曾理 吴宜佳 王增杰 胡晓波 编辑:胡彦 周永康 张诗婧 吴丹丹
叶飞 徐虎 杨荣华 边福军 桑秀菁 边媛 刘晓茜 程鹏 王平 美编:吴山 谭嘉敏 张钥 杨俊 技术:梁瑛玮 江玲
主编信箱 热线:010-82558255 给网易提意见
About NetEase - 公司简介 - 联系方法 - 招聘信息 - 客户服务 - 相关法律 - 网络营销 - 帮助中心
网易公司版权所有
©1997-2008